Installation Instructions
- First time NUHEAT installers
are required to contact
the distributor during the planning stages.
- Projects over 1,000 square feet
of NUHEAT require a pre-installation conference between the designer,
the installer and an authorized NUHEAT representative.
|
|
Return to Nuheat
Main Page |
A: Helpful
Tips
B: Unpacking
and Handling
C: General
Floor Preparation
D: Testing
E: Electrical
Preparation
F: NUHEAT
Installation By Specific Flooring Type
G: Controls
& Accessories Available Through NUHEAT
H: Trouble
Shooting |
|
- A) HELPFUL TIPS
CONDUCT RESISTANCE AND INSULATION TESTS ON THE NUHEAT MATS(S)
"BEFORE", "DURING" AND "AFTER"
THE INSTALLATION PROCESS IN ORDER TO MAINTAIN THE 25-YEAR WARRANTY.
(See Section D)
All first time tile installers and electricians are required
to contact us prior to the NUHEAT installation. At this time,
a technical representative will briefly clarify critical installation
procedures. Failure to follow this instruction will void the
25-year product warranty.
Please read the installation instructions completely and use
NUHEAT with caution appropriate for an "electrical"
and "heating" product.
Choose which controlling device(s) are required before installing
NUHEAT; especially if installing the floor-warming control with
G.F.C.I.
NUHEAT 25-year product warranty applies under ceramic tile, marble
and natural stone installations only.
Allow at least 72 hours to 1 week for the mortar to cure, or
according to manufacturer specifications, before activating NUHEAT.
It is mandatory to install a Class "A" G.F.C.I. or
G.F.C.I. circuit breaker with each NUHEAT installation. NUHEAT
must be installed on a dedicated circuit.
When planning
your heating layout:
Measure the area(s) to be heated to determine which NUHEAT mats
will fit your application.
Allow for obstructions (vanities, vents, exposed plumbing, etc.).
Remember that NUHEAT mats have no "up" or "down"
side -- mats may be placed side by side maintaining at least
1" clearance between the heating wires.
There is little or no horizontal heat travel. Please consult
us for design and sizing assistance. TOP
|
|
|
B) UNPACKING
AND HANDLING
I)
BEFORE, DURING & AFTER INSTALLATION
Conduct resistance & insulation tests on the NUHEAT mat(s)
at least three times during the installation process. See Section
D for more information.
II) DURING
INSTALLATION
Avoid the following activities that may damage NUHEAT:
- unnecessary folding
- walking on unit (protect with
a cover like plywood)
- stapling
- nailing
- dropping heavy objects on NUHEAT
- Do Not Use grout scrapers
or exacto knives to clean grout joints. Cleaning grout joints
with sharp tools may damage the NUHEAT mat. Using these tools
will void the NUHEAT warranty.
III) AFTER
INSTALLATION
Allow your NUHEAT to "breathe" by avoiding "zero-clearance"
furniture (i.e., solid oak cabinets, etc.).
Ensure that new occupants are
aware that NUHEAT is installed in the home. |
|
TOP |
|
|
|
|
C) GENERAL FLOOR PREPARATION
Ensure that the subfloor is free of debris and suitable for the
floor covering before installing the NUHEAT mat(s). |
|
|
D) TESTING
DO NOT CONNECT MAT TO POWER DURING TESTING
I) INSULATION
TEST
To ensure that the copper conductors are fully insulated:
- acquire an ohmmeter or equivalent
testing device
- place one meter probe on the
ground (outer metallic braid) and the other probe on the copper
wire inside the white lead
- confirm that the reading is
1 million ohms to infinity
- repeat these steps to check
the reading between the metallic braid and the copper wire inside
the black lead
ll) RESISTANCE
TEST
To ensure continuity in your heating mat:
- acquire an ohmmeter or equivalent
testing device
- set the ohmmeter to the lowest
setting
- place one of the meter probes
on the copper wire in the white lead and the other probe on the
copper wire in the black lead
- check to see that your reading
in ohms closely matches the reading listed on the tag of the
mat being tested.
NOTE: NUHEAT MUST BE TESTED BEFORE,
DURING AND AFTER INSTALLATION TO VALIDATE THE WARRANTY. |
|
TOP |
|
|
|
|
|
E) ELECTRICAL PREPARATION
Recommendations:
All wiring must follow specifications set out in Part 1 of the
Canadian Electrical Code, the US National Electrical Code and
local electrical inspection regulations. All NUHEAT units must
be connected to the electrical service through a Class "A"
Ground Fault Circuit Interrupter.
INSTALLATION
STEPS:
- Connect the braided ground wire
to the electrical box ground screw and attach to the G.F.C.I.
with a standard ground copper conductor.
- Attach the connecting wires
to the outlet box using CSA Certified/UL Listed cable fittings.
Tighten the diameter of the cable fittings to 1/5" (5mm)
to secure the connection.
- Make the electrical connection
only after the flooring is complete. Whenever possible, the connecting
cable should be laid in low traffic areas.
|
|
TOP |
|
|
|
|
|
F) NUHEAT
INSTALLATION UNDER CERAMIC TILE, MARBLE AND NATURAL STONE
Recommendations:
To ensure a successful installation, NUHEAT recommends high quality,
factory thin set mortars meeting the requirements of ANSI A118.4.
- INSTALLATION
STEPS
- Mark the locations of the connecting
cable and connection patch on the subfloor. Lay out the path
of the 10' lead to the wall box around the perimeter of the NUHEAT
mat(s). (Conduct TEST #1)
- Using at least a 1/4" x
1/4" square notch trowel, lay a coat of fresh mortar over
the area to be covered by NUHEAT.
- Place NUHEAT onto the fresh
mortar pressing firmly with grout float or lightweight roller.
Create 100% contact between the heating unit, the mortar and
the subfloor. Make sure that there are no air bubbles or curls
and that the surface is flat to receive tile.
- If leaving overnight, place
a skim coat of mortar over the surface of the NUHEAT mat to cover
it completely. Level the areas of the floor that are not covered
by the NUHEAT mat(s). (Conduct TEST #2)
- If installing a floor-warming
control with G.F.C.I., ensure that the floor-sensing probe is
installed at this point.
- Set the tile on the NUHEAT.
Tile must be installed according to requirements of ANSI A108.5.
(Conduct TEST #3)
Clean the grout lines with a damp sponge/cloth as tile is being
laid. The use of grout scrapers or exacto knives to clean grout
joints will void the NUHEAT warranty.
NOTE:
Do Not Use grout scrapers or
exacto knives to clean grout joints. Cleaning grout joints with
sharp tools may damage the NUHEAT mat. Using these tools will
VOID THE NUHEAT WARRANTY.
Before activating NUHEAT, allow
the mortar and grout to cure 72 hours to 1 week or according
to manufacturer guidelines. |
|
TOP |
|
|
|
|
- G) CONTROLS & ACCESSORIES
AVAILABLE THROUGH NUHEAT
Floor-Warming Control with G.F.C.I.
NOTE: Please call the Distributor for further details regarding
installing the appropriate controls.
|
|
|
H) TROUBLE
SHOOTING
Please contact NUHEAT TOLL-FREE
directly at 1-800-778-9276 should you have any questions or difficulties
installing or controlling your NUHEAT mat(s).
INSTALLATION
NOTES:
Reminder:
All first time tile installers and electricians are required
to contact the manufacturer prior to the NUHEAT installation.
At this time, a technical representative will briefly clarify
critical installation procedures. Failure to follow this instruction
will void the 25 year product warranty. |
|